Weir Power and Industrial Suzhou

Weir Power and Industrial Suzhou redefine the possibility of improvement on On Time Delivery

To focus on improvements in customer service Weir Power & Industrial Suzhou has made great improvements in on time delivery performance.

A task team has been created to review previous sub-optimal performance and identify the root causes to enable a focus on the improvement activity. By using workflow analysis tools, value stream analysis (VSA) and 3Cs, five target issues were identified.

As a result, a number of targeted initiatives have been created including a new production planning model; Multi-skilling of Shop floor operators.

Re-organised shifts resolved production bottlenecks. The outsourcing strategy was revised to balance the capacity and the Introduction of periodical planning review meetings hosted by our master scheduler, for better information flow and much improved controls.

The overall effect was that on time delivery performance has now improved to 98% in 2009, far exceeding our original expectations.